On DRDO’s biggest criticism of failing to
deliver in time, resulting in delays and time and cost overruns.
To understand this issue, you will
have to go back to history a bit, the time when DRDO was set up in 1958 with practically no
idea of what defence research will be. There was no defence technology at that
time, DRDO was created from a set of institutions which were set up by the
British for doing quality assurance and to some extent reverse engineering of
products which were manufactured in British ordnance factories and brought to
Indian ordnance factories for mass scale production. That was the scenario in
which defence research started. Our leaders like Jawaharlal realised that
overdependence on equipment which was of British origin or was left behind as
part of Commonwealth legacy was not adequate. They realised that there should
be a push to defence research.
It was under the leadership of D. S. Kothari, the first
Scientific Advisor, that a complete framework of defence research was set up.
The vision of our own planners was very limited. They said that India needs
only small things and not big things. So six or seven areas were identified
which included missiles, material, electronic systems and so on. Many of these
were derivatives of technological institutions of Britishers. Obviously, they
did not have any background of defence research. Starting from that era, DRDO
started building technologies.
Fortunately there was this public
sector set up of Bharat
Electronics Limited (BEL) which had a collaboration with Thalys of France. It helped in
converting the research of DRDO into production of mostly communication
equipment for our armed forces.
Initially, it built some radars.
Our armed forces were being equipped by acquisition of equipment which was
either British or Russian because in late 50s and early 60s we had good
equation with Russians. Indian equipment was in sporadic supply, in fact, it
was hardly anything because we did not have any industry. Tatas and Birlas were
into very mundane commercial production, Tatas had set up their steel plant.
Inputs needed for manufacturing any goods were barely available in the country.
In 1963, we started our first
indigenous anti tank missile programme which started here and was later shifted
later to Hyderabad. In 1963-64, we started indigenous anti-tank missile
programme. My predecessors had to assemble a nine volt dry cell to power the
missile in the lab. The famous Exide which was making automobile batteries was
not in a position to do anything. There was no industry both in the country
private and public sectors that could have helped DRDO in doing anything.
So, industry non-existent,
technology base not there, academic institutions of excellence not present but
individual excellence was available in giants like Prof. Kothari and Dr.
Sarabhai. But large scale academic excellence which is needed for doing this
kind of work was not there.
Era of 70s
Between 1960-70, DRDO started
building technology and this was in radars, missiles, communication and
materials area and to some extent electronic warfare. This is our own
technology. There was another parallel push in DRDO, we took up reverse
engineering of available products which our armed forces were having at that
time.
One is own technology development,
and then through reverse engineering. These two processes were on at the same
time. Until 70s the participation of Indian private industry was practically
non-existent. The only area where we were getting support was the growth of
BEL, HAL and then in 1968-69 came in Bharat Dynamics Limited (BDL) which was
part of a project which DRDO did although the project was shelved. There were
60 to 70 scientists who had soiled their hands in missile development and they
were available to set up BDL. Right from the general manager to technician were
from DRDO. It was in 70s when DRDO really grew, major emphasis was placed by
Dr. Nag Chaudhary on missiles. While Atomic Energy Department was working for
first nuclear explosion which finally took place in 1974, that was also the
time when present crop of people like us from IITs, and Indian Institute of
Science came around. These institutions produced about a hundred engineers and
they were inducted into the system to work on technology development.
In the 1970-80 decade, DRDO
technology grew in all spheres. there were giants like Prof. MGK Menon and Dr.
Raja Ramanna who had become Scientific Advisers. I was responsible for
manufacture of liquid rocket engine. The first Indra One radar came in that
period. Prof. Narain Rao had built jammers and even at that time participation
of industry was limited to public sector but DRDO could not survive purely by
interacting with only public sector. Two private sector industries started
working with DRDO. There was this Prof Janardan Rao who came from the U.S. and
set up a small unit. When I was doing liquid rocket engine programme I needed
electro pneumatic system for testing. Under a shed in most abysmal condition,
he was trying to do most sophisticated and advanced technology with whatever
money he got from the U.S. He built the electro pneumatic system for me that
enabled first liquid rocket engine testing possible. If it was not there, I
would not have been able to test. Like that there were hundreds of such
scattered stories where we could trigger small and medium Industries.
At the same time, Department of
Space and Atomic Energy were also having similar experiments. It was an era
when a good number of medium and small scale industries came up. What handicap
we faced in 60s of assembling our own dry cell had vanished and as a result of
that some good products came, communication sets came, good radars also came.
Indra One radar was given to our armed forces. People thought it was a never
ending process. Time required was enormous; we did not have the advantage of
the global eco system. India had missed the industrial revolution and it did
not have an industrial background but had embarked upon an ambitious defence
technology programme which at that time was ahead by leaps and bounds in
foreign countries who were already flying missiles and aircraft and developing
new technologies but India was only using systems imported from various
countries.
India also did not have the
advantage of the licensed productions which were signed during 50s and 60s
during the socialist pattern of governance in which large number of public sector
units were set up. They could not contribute to technology development as all
of them were licensed production agencies. They were continuously going from
one licence to another. DRDO, Space and Atomic Energy none of them could
benefit from licensed production culture which was prevalent in India. We had
to do technology development by ourselves.
80s saw DRDO graduating to weapons system
In 1980 when Mrs Indira Gandhi
returned to power, she said DRDO has spent a lot of time now and the country
had started asking the same questions which are being raised now. We had
completed small programmes. Mrs. Gandhi said that time has come for you to consolidate.
We had four technologies going on in DRDO – surface to air missiles, new
generation anti-tank missile and also as part of Dr. Nag Chaudhary’s vision we
were planning to do a long range ballistic missile that has led to development
of propulsion technology in DRDO. I fired 30 tonne liquid rocket engine in 1974
and it was all being developed and so when Mrs. Gandhi saw all this, she said
it is time for you to graduate to weapons system.
With her vision and induction of
Dr. Arunachalam as Scientific Advisor and Dr. Abdul Kalam as the Director of
DRDO, she entrusted the task of building missiles for the country and that gave
birth to IGMDP --the Integrated Guided Missile Development Programme (IGMDP).
It was not only given projects but it changed complete structure and system of
working of DRDO. When we analysed reasons for delay, one of the issues which
came out was that we did not have the availability of large scale production of
indigenously developed products. We were doing licensed production but we did
not know how to produce in terms of quality and quantity the indigenously
developed products.
Her vision reflected into a very
potent management structure. IGMDP’s three-tier management system –
development, production and risk taking facility. She said production
facilities of the country would be augmented and the programme was having the
necessary funds and the risk taking capability that in case these projects
failed this infrastructure would not be terminated. That vision led to the
growth of HAL, BEL and BDL.
In this long journey of developing
our defence sector, you will see that delays took place due to non-availability
of products. It was during Mrs. Gandhi’s time that our public sector developed
risk taking capability and BDL, HAL, BEL took on production of IGMDP systems.
In 80s, we set up aerospace
division of HAL, it was set up when I was doing the Prithvi programme. We also
first developed the airframe of Prithvi missile and the division was set up at
a cost of Rs. 46 crore. At that time ISRO was setting up PSLV integration
programme, so we joined hands and this led to upgradation of production,
capacity to take risks and also monitoring and management of variety of
institutions in the country was set in.
Decision makers at that point in
time asked me why delays were taking place. I said that maximum delay took
place in procuring the materials and equipment for doing the product and which
is 40 per cent of the time of the production cycle. The then Expenditure
Secretary Mr. Ganpati said that you should not follow the typical process of
getting quotations and he said that when you deal with public sector units all
your contracts should be on the cost plus basis whether it is BDL, BEL or HAL.
He fixed that 12 per cent will be profit and said that HAL cannot take more
than that. In today’s parlance, I cannot even think that something like this
will happen and IGMDP worked on this pattern and this aggressive decision
making enabled a good ecosystem for R & D and which got converted into production.
On Prithvi and Agni Missiles
We were to develop Prithvi
missile’s one version in seven years but we developed three versions in 15
years – first of 150 km range, second of 250 km and the third naval version of
350 km range when fired from the ship, yes we took 15 years but we developed
the complete system. Same thing happened in Agni One, Two Three programme. But
still time and cost overruns were there because when IGMDP was planned we had
planned to import some material. We had to import some materials for Prithvi
which was first fired in 1988 and Agni in 1989 and then MTCR (Missile
Technology Control Regime) which was brewing all this time clamped all
restrictions on us. All the contracts which we had signed with all companies
were not honoured and these companies took back everything. Everything was
denied to us, this denial caused us a lot of delay and whatever we needed had
to be designed, developed and produced by us.
From 1989 to 1997 was a harrowing
period. There were restrictions imposed on India and for things like getting
Magnesium supply and Servo valves for launch vehicles, we had to struggle and
later produce our very own. At that time, Tamil Nadu government’s TIDCO helped
in making Magnesium slab from ore. Though technical problems had been solved by
first launches of Prithvi and Agni missiles. Now these problems are not there,
Today, India produces its own servo valves not only for missiles but also for
launch vehicles and many other industrial purposes. What was a critical technology
in 1988 is no more critical, new technologies have come. A lot of
liberalisation has taken place but the fact still remains that critical
technologies which are required are not available to us. For example, we still
do not have access to high end computer processors and we have to make do with
Intel core system. I cannot get a high end computer and I have to start
building it for my missile right from the chip.
On delays in development and
production of Arjun Main Battle Tank and Light Combat Aircraft (LCA)
Nearly three decades ago, Arjun
tank project was started and after that we started work on Light Combat
Aircraft (LCA). These got delayed mainly due to denial of several technologies
to us and lack of industrial support. We have done LCA-LCA MK.1 which is going
to be produced. We are doing LCA-MK.2 and also doing LCANavy. LCA Navy will be
able to take off and land on deck of a ship. We are building all facilities for
a short lift, short take off, short landing, all that we are doing. Arjun Mark
2, we have made 66 modifications in three years. First set of trials are over
last summer, second set of trials are going to be held this year. We have
demonstrated missile firing capability just about a month and a half back.
LCA MK 2 is now a reality on the drawing
board because we are in a position to get industrial support and academic
support so these delays which used to happen earlier, the causes have been
removed, the eco system is much more friendly than ever before. Experience of
doing large scale products has also come to us which was not there in 60s and
70s.
On Indigenisation, where India stands
today? Increase in FDI limit.
Today, DRDO has groomed 400
industries and has their support. We have galloped in electronics.
Semi-conductor technology and high end computing chips were denied to us by the
West but we have gone ahead and we are putting up a state-of-the art foundry
for manufacturing semi-conductors.
Today if I want a rocket motor I
can go to Godrej or Walchandnagar or to BDL. Today if I want a computer I can
go to private industries and hundreds of them are available. I can give
specification of a launcher to at least ten industries in this country who can
manufacture one. If I want a system integration, my public sector units can do
that whether it is HAL, BDL or BEL, they can do overall lead system
integration. Still there are gaps and these gaps are continuously increasing
because in areas of electronics technology has galloped. What was 8086 computer
of Prithivi with 64 kb memory is now into gigabytes of memory. So, we had
missed that completely, our semiconductor technology is lagging behind. At
least R & D should have gone into it but we were denied all semiconductor
equipment and machinery from the West.
New area of photonic system has
come. If I have close tie ups with international community in these areas the
pace with which this gap has to be filled will never be achieved. So we have to
get tie ups with extremely high investments. A good foundry will cost two to
three billion dollars, we need to have it. In my view, joint ventures (JV) and
stress on indigenisation is the core of our strategy to move forward. But JV
cannot come up with the limitation of FDI. If you want to get really good
technology, it will not come with 26 per cent. It should be raised to 48 to 49
per cent so that we can get required good technology. But there are fears in
the minds of people if we allow more than that the process of indigenisation
will suffer, I can say that indigenisation will not suffer because Indian
R&D is not so weak today that it cannot compete with the R&D in the
world.
In the last 10 to 15 years I have
worked in international collaboration with Russia, France, Israel, and I can
only say that Indian R&D institutions and scientists are matching one to
one with respect to best of their capabilities to contributing to JV or
absorbing from there the right technology. This is not going to be teacher and
taught relationship. This is going to be a relationship at par. Our research
base and eco systems are strong enough to grow further with these partnerships.
We learnt how to do professional
management of development of large systems using multiple agencies and bringing
all of them in terms of time, technology coherence and in terms of joint
motivation to achieve the goal has been learnt by this organisation. And this
is unique feature of three departments -- DRDO, ISRO and Atomic Energy.
These are the only three
departments who are in a position to do this kind of large system, development
which you will see still lacking in other departments.
On China and how India is closing gaps in
technology; Private sector should not remain only a component manufacturer
Only gap which exists between
China and India today is in terms of large scale manufacturing capability. As
far as technology is concerned, I can only say in defence we have come very
close to China. Take missiles, our reach and accuracy is comparable. Today we
have no problem.
Our LCA today is a shining example
of comparably what China is producing in J-10. Our LCA is today fourth
generation plus aircraft. But our manufacturing capabilities in numbers are
certainly lacking and that is where gap has to be caught up. That is where
private sector participation and a trustworthy platform and ecosystem which
will bring private sector as an agency that is as competent, as good, as
patriotic and as nationalistic should be considered. That ecosystem should be provided
to private sector to come in whether it is shipbuilding, missile building,
torpedo building or submarine building. We should not allow private sector to
remain a component manufacturer. We should let them graduate from sub system
manufacturer. Private sector should graduate to a lead system integrator and
then certainly we can catch up with China in no time.
On future missile programme
In the area of long range
missiles, our programmes are well defined. We are doing technologies which will
be integrated with Agni V and then we are also trying to see the ballistic
missiles of different ranges in different roles. We have already been strategic
roles but there are tactical roles of ballistic missiles emerging. War is not
going to be just across our boundaries, it will be in far off places and across
continents. So what we are looking today how to make sure that ballistic
missile reach precisely like China has done today anti-ship ballistic missile,
we have plans to convert some of our ballistic missiles to take on pinpoint
mobile targets.
Ballistic missile defence is our
priority area which we are augmenting in a big way. Going from our interception
capability of 80 kms to 300 kms, we are also having the capability to take care
in a limited manner of sudden large number of missiles fired.
Of course you cannot handle
infinite missiles coming; there is no answer to infinite missiles. If somebody
is launching 24 missiles at the same time, we should be able to handle it, Our
emphasis is on missile development programme and going for cruise missiles,
like you saw the launch of Nirbhay last time. And we have to perfect that
system.
In the case of ballistic missiles,
we are trying to get precision guided ammunitions being released from a mother
missile for shorter range like 300 kms. One missile releasing about six to
seven precision guided missiles which can home on different targets. Our
strategic requirement is almost getting met, and we are not in any kind of race
in that area. We may cover strategic requirement based on our threat
perception. Tactical arena requires precision guided missiles, cruise missiles,
short range missiles. Prahar missile is going to be given to artillery for
short range targets of about 100 kms plus. Accuracy of our missiles is less than
10 metres with various weights and volumes. We were denied certain facilities
like good sensors and we developed our own navigation system and we are in a
position to play with weight and volume. There is no more gap between India
missile and the Western missile.
We are shrinking slowly to
reasonable numbers and managing with our indigenous capability. Indigenisation
has gone up from 30 per cent in the 90s to 50 to 55 per cent and it needs to go
further up to 70 per cent.
No comments:
Post a Comment